Nitrogen Unit | Ropa a plyn | Probíhající | Irák | EPC project | Midland Refineries Co., Iraq | Capacity: 1500 NM3/hr |
Crude Distillation Unit 70 000 BPSD | Ropa a plyn | Probíhající | Irák | EPC project | SRC (South Refineries Company)., Iraq | Crude Distillation Unit 70 000 BPSD, LPG unit, Boiler Unit, Flare unit and Interconnecting piping |
Water Treatment Unit for Ammonia Plant Kingisepp | Úprava vody a odpadních vod | 2019 | Ruská federace | EPC | LLC TECNIMONT Russia | Highly desalinated water stream (180 m3/h), Recirculation feed stream (820 m3/h), Firefighting system feed (200 m3/h), Concentrate stream (60 m3/h), Storage facilities and logistics |
Aniline plant | Anilin | 2013 | Slovenská republika | Technical and commercial study | Duslo Šala, Slovak Republic | Aniline plant - Aniline unit, Nitrobenzene unit, Hydrogen unit, raw material unloading, product loading, tank farm |
Spare parts for NDCU Daura II | Ropa a plyn | 2013 | Irák | Procurement and delivery | Midland Refineries Co., Iraq | Crude Distillation Unit 70.000 BPSD |
Isomerization unit | Ropa a plyn | 2013 | Irák | Detail desing, procurement, supervision of erection, commissioning, start-up, trial run and performance quarantee test, training of personnel. | Hydracarbon, Jordan (Ministry of Oil) SCOP, Iraq | Detail design and procurement assistance |
Completion of the Isomerization | Ropa a plyn | 2011 | Irák | Verification of status,check of material,equipment,recommendation forcorrective actions, new detail design,procurement, erection,commissioning, start-up,trial run and performanceguarantee test, training of personnel. | Ministry of Oil, North Refineries Co., Iraq | Completion of the Isomerization. Process design licensor/Technology supplier: UOP (England) |
Enhancing of gasoline product | Ropa a plyn | 2011 | Irák | Basic and Detail desing, Supervision, commissioning, start-up, trial run and performance guarantee test, training of personnel. | UNIS, s.r.o. / Ministry of up, Oil, performance South of Refineries Co., Iraq | XXXX |
Biodiesel unit Oil Treatment unit | Bionafta | 2010 | Česká republika | Turn-key project (including auxilliaries) | PREOL, a.s., Czech Republic | Processing of 400 000 MTPY of rape seeds into oil followed by production of 100 000 MTPY of methylester of rape seed oil (FAME) and glycerine. The unit consists of pressing plant, extraction, chemical oil treatment, FAME and pharmaglycerine production Raw material: rapeseed and other oils (palm oil, soya oil). Technology: Desmet Ballestra |
Improvement of safety on the unit 25 | Ropa a plyn | 2009 | Česká republika | EPC project | Česká Rafinérská, a.s., Czech Republic | Replacement of 22 burners including supplementation of 132 EMS valves to piping of gas fuel of 9 refinery preheating furnaces including |
Diesel oil storage capacities | Ropa a plyn | 2009 | Česká republika | Planning and building permission, documentation for supplier selection in international bidding process, Detail design, supervision, documentation for complex testing and pre- commissioning, as-built documentation. | Ministry of Defence, Czech Republic | Entry, storage and handling of diesel oil. Capacity: 2x5000 m3 |
Butadiene production unit | Ropa a plyn | 2009 | Česká republika | Turn-key | Butadien, a.s. (owner is Unipetrol, a.s. and Kaucuk, a.s.) | Butadiene production Capacity: 120 000 MTPY Technolgy: JSR Corporation (Japan) |
2AF22024 Storage of jet oil | Ropa a plyn | 2009 | Česká republika | Planning and building permission, documentation for supplier selection in international bidding process, Detail design, supervision, documentation for complex testing and pre- commissioning, as-built documentation. | Ministry of Defence, Czech Republic | Entry, storage and handling of diesel oil. Capacity: 4x1000 m3 |
Biodiesel unit Oil Treatment unit | Bionafta | 2008 | Slovenská republika | Turn-key project (including auxilliaries) | MEROCO, a.s., Slovakia | Physical deacidification of degummed oil. Sunflower oil dewaxing unit. Three - stage continual estherification of neutralised oil into methyl ester. Capacity: 100 000 MTPY. Technology: Desmet Ballestra |
Biodiesel unit Oil Treatment unit | Bionafta | 2007 | Česká republika | Turn-key project (including auxilliaries) | SETUZA, a.s., Ústí nad Labem, Czech Republic | Physical deacidification of degummed oil. Three - stage continual estherification of neutralised oil into methyl ester. Raw material: vegetable oils (rape seed, soya, palm) Capacity:100 000 MTPY. Technology: Desmet Ballestra |
Renewal of aniline distillation unit | Anilin | 2007 | Česká republika | Basic and Detail Design | BorsodChem MCHZ, s.r.o., Czech Republic | Renewal of aniline distillation unit |
Alarm system of the AVD furnaces and hydrogenation chamber K5/6 | Ropa a plyn | 2007 | Česká republika | EPC project | Česká Rafinérská, a.s., Czech Republic | Modification of piping of gas fuel refinery preheating furnaces including new EMS valves and supplementation of TRICONEX system |
Renewal of storage capacity for fuels | Ropa a plyn | 2007 | Česká republika | Turn-key project (including auxilliary operations) | CEPRO a.s. Czech Republic | Construction of 4 boilers with capacity of 10 000 m3, including extinquishing, fuel stations and pipelines. |
Renewal of hydrogenation unit for Aniline production | Anilin | 2006 | Česká republika | Turn-key | BorsodChem MCHZ, s.r.o., Czech Republic | Construction of another new hydrogenation train. Capacity: 40 000 MTPY |
Aniline unit | Anilin | 2005 | Japonsko | Basic design and technical assistance during detail design and start-up. | TOSOH, Japan | Construction of a new unit Capacity: 150 000 MTPY. |
Biodiesel unit | Bionafta | 2005 | Česká republika | EP project (FS, EIA, BP, IPPC) | SETUZA, a.s., Ústí nad Labem, Czech Republic | Intesification of the unit from 12 000 MTPY up to 30 000 MTPY and modification from batch to semi-continual production Technology: STZ+SEPARA Brno |
Biodiesel unit | Bionafta | 2005 | Česká republika | EP project (FS, EIA, BP, IPPC) | SETUZA, a.s., Ústí nad Labem, Czech Republic | Intesification of the unit from 12 000 MTPY up to 30 000 MTPY and modification from batch to semi-continual production Technology: STZ+SEPARA Brno |
Intensification of Aniline unit | Anilin | 2005 | Česká republika | Hydrogentation train - Turn-key, New hydrogen unit - building permit documentation., Detail design off-sites. | BorsodChem MCHZ, s.r.o., Czech Republic | Intensification of aniline unit up-to total capacity: 150 000 MTPY of aniline. New hydrogenation train of capacity: 40 000 MTPY, and new hydrogen unit of capacity 6 000 Nm3/hr. |
Operation renewal of chamber K 11 and D distillation | Ropa a plyn | 2004 | Česká republika | Execution of complete inspection of performed equipment in mechanical, civil, electrical part and control system and field instrumentation, EPC, basic design engineering package for putting into stream of chamber and distillation. | Česká rafinérská, a.s. (UNIPETROL RAFINERIE a.s.) | High-pressure hydrogenation of 24 t/hour vacuum distillate including distillation. production of hydrogenated oils for ethylen unit and production of oils. |
Oxo products loading to trucks | Ropa a plyn | 2004 | Česká republika | Turn-key | Chemopetrol, a.s Litvinov, Czech Republic | Loading place for oxo products loading to trucks, upper loading - PC automatic control. Loading capacity: 30 m3/hour |
Polyphenylenether unit | Ropa a plyn | 2004 | Čínská lidová republika | Extended BD, procurement, consultancy, supply of proprietary equipment, supervision at the site and during commissioning period. | Ruicheng First Chemical, Ltd., China | New polyphenylenether production unit. Process know-how was supplied by Cheminvex, s.r.o., Czech Republic. Capacity: 32 MTPD (10 000 MTPY) of polyphenylenether. |
Hydrogen unit # 2 | Ropa a plyn | 2004 | Maďarsko | Basic design for Koch- Glitsch (the process know-how supplier). Complete detail design consisting of process, civil, mechanical, electrical and instrumentation engineering parts for the main contractor Skoda JS. | Snamprogetti Limited/ MOL refinery | Haldor Topsoe process with capacity 40 000 Nm3/ h with 40% turndown. Feedstock: natural gas and fresh water. |
Rehabilitation of Natural gas unit | Ropa a plyn | 2004 | Česká republika | Basic design for Koch- Glitsch (the process know-how supplier). Complete detail design consisting of process, civil, mechanical, electrical and instrumentation engineering parts for the main contractor Skoda JS. | Skoda JS / Koch-Glitsch, Czech Republic | Natural gas plant rehabilitation. Capacity: 3 bn m3 / year of desulphurised gas, LPG, liquid propane and stabilized condensation. |
Water system utilities | Úprava vody a odpadních vod | 2003 | Česká republika | Documentation for planning permission proceesings, building permint documentation, DD, supervison | TPCA Kolin (Toyota, Peugeot, Citroen), Czech Republic | Water system including sewage treatment plant. |
Shutdown 2001 | Ropa a plyn | 2003 | Česká republika | Turn-key | Ceska rafinerska, Czech Republic | Reconstruction of sampling places in refinery Litvinov. |
Polypropylene unit | Ropa a plyn | 2003 | Slovenská republika | Detail design for civil part and steel structures related with PP ISBL. EPC PP pellet silos storage facilities - civil, steel structures, electrical & instrumentation. | Linde / Slovnaft | New Polypropylene (PP) unit and Offsites. |
Gasification liquid by-products for fuel gas production | Ropa a plyn | 2003 | Česká republika | EPC (including purchasing the technology from Future Energy, GmbH and supplying the combustion reactor. | Sokolovska uhelna, a.s. | Technology for liquid by product combustion is used for utilization liquid wastes produced during the coalgasification proccess. |
Fractionation – refinery Novopolock | Ropa a plyn | 2003 | Bělorusko | DD, supervision | Koch-Glitsch/ Naftan Novopolock | Fractionation unit for Hydrocrack. Process licence: Koch-Glitsch. |
Hydrogen unit- refinery Novopolock | Ropa a plyn | 2003 | Bělorusko | DD, supervision | Unis/ Naftan Novopolock | Hydrogen unit, Process licence: Koch-Glitsch. |
Intensification of HDPE unit | Ropa a plyn | 2001 | Belgie | Front end engineering design, detail design. | Technip France | Intensification of HDPE (High Density Polyethylene) production plant. Process licence: Solvay. Capacity: 250 000 MTPY. |
Polyolefin storage | Ropa a plyn | 2000 | Česká republika | EPC project | Chemopetrol, a.s., Czech Republic | New high-capacity storage equipment for granulated PE and PP inclusive of expedition section. Total storage capacity: 9 000 t (3 600 t in silos) |
Silica activation unit | Ropa a plyn | 2000 | Česká republika | Extended basic design, detail design, procurement, delivery, erection, commissioning, start-up. | Linde (GER)/ Chemopetrol, a.s., (CZE) | Activation of Silica (Polyolefin catalyst carrier). Capacity: 500 kg/ d (two process units 250 kg/day each). |
Asphalts loading to trucks | Ropa a plyn | 2000 | Česká republika | EPC project | Ceska rafinerska, Czech Republic | Extension and renovation of asphalts loading to trucks. |
Tankfarm A reconstruction | Ropa a plyn | 2000 | Česká republika | Turn-key | Ceska rafinerska, Czech Republic | Asphalts tankfarm reconstruction - pumping station and piping distribution system. |
Corinth refinery upgrading | Ropa a plyn | 2000 | Řecko | Detail design documentation of Hydrotreater and Benfree units. Engineered to ANSI standard and designed with the aid of Intergraph PDS 3D modelling software | Technip / Motor Oil Hellas | Benzene removal from diesel fuel by hydrogenation with 400 000 MTPY processing capacity |
Vacuum distillation revamp | Ropa a plyn | 2000 | Uzbekistán | BD, DD-piping section, supervision, start-up. | Koch-Glitch Brno, Czech Republic | Reconstruction and intenzification of production. |
New control centre | Ropa a plyn | 1999 | Česká republika | Planning and building permit documentation, detail design. | Armabeton, a.s. for Ceska rafinerska, a.s., Czech Republic | Construction of new control centre for centralised process supervision. |
Independent firefighting water system RL 98025 | Úprava vody a odpadních vod | 1999 | Česká republika | Elaboration of BDEP, building permit documentation. | Ceska rafinerska, a.s. Litvínov, Czech Republic | Review of existing fire extinguishing system in Czech Republic, survey for a new pumping firewater station, new firewater distribution system, foam extinguishing system and construction of product tankfarm. |
Stable fire suppression system | Úprava vody a odpadních vod | 1998 | Česká republika | Turn-key (including erection) | Foster Wheeler, Czech Republic | Fire water distribution, portable and semi-stable fire extinguishing device. |
Carbohydrate storage, RL-9607. | Ropa a plyn | 1998 | Česká republika | Turn-key | Ceska Rafinerska, a.s. Czech Republic | Revamping of existing underground storage tanks and LPG store, construction of new VNR, LPG pump stations and loading of LPG into trucks (rail and road). |
Intensification of Aniline production | Anilin | 1998 | Česká republika | Design documentation fo building perming, detail design, supervision. | MCHZ Ostrava, Czech Republic | Intensification of aniline production from 75 kt/year up to 110 000 MTPY. Nitrobenzene production (Plinke). Revamping of: Nitrobenzene clarification unit, loading and unloading of storage tanks. Reconstruction of material and end product storage. |
Relocation of two production lines | Ropa a plyn | 1998 | Česká republika | Detail design | Silon Plana a.s. Czech Republic | Relocation of two production lines for polyolefins to new building including revamping of second lines. |
Inventarization of actual waste water treatment system. | Úprava vody a odpadních vod | 1997 | Česká republika | Inspection of existing waste water handling system. test results elaborated in the as-built documentation. | Ceska rafinerska, a.s. Kralupy, Czech Republic | Inventarization of actual waste water handling system. |
Reviewing of existing waste water management system | Úprava vody a odpadních vod | 1997 | Česká republika | Consulting services | Ceska rafinerska, a.s. Kralupy, Czech Republic | Review of existing waste water management system. |
Cooling circuit for Butadiene production | Úprava vody a odpadních vod | 1997 | Česká republika | Feasibility study. | Kaucuk, Kralupy, Czech Republic | Capacity: 3 000 m3/ hour |
Waste water storage | Úprava vody a odpadních vod | 1997 | Česká republika | Turn-key | CEZ a.s., Praha - Power station Chvaletice. Czech Republic | Waste water storage, desulphurization. Capacity: 2 x 350 m3 |
Savage treatment facility | Úprava vody a odpadních vod | 1997 | Česká republika | Feasibility study, Basic and Detail design (civil part), Supervision, Commissioning. | CSA - airport Ruzyne - North and South, Czech Republic | Rain and sewage water treatment. Capacity: 80+100 m3/ hour. Actual efficiency : 87 - 93 % (BSK5). |
Fuel depot – Moravian steel – mill | Ropa a plyn | 1997 | Česká republika | Design package, environmental impact assessment, procurement, engineering, complex testing, geologic and geodetic survey. | ŐMV, Czech Republic | Storage capacity: 4 500 m3, loading and unloading of fuels and lubricants for the territory of Moravia midland. |
Adding fuel catalysts into gasoline and diesel fuels | Ropa a plyn | 1997 | Česká republika | Turn-key Staff training, complex testing. | Ceska Rafinerska a.s., Czech Republic | Storage tanks for 8 kinds of additives, automatically operated truck loading. |
Fuel loading facilities for trucks | Ropa a plyn | 1997 | Česká republika | Design package, supervision, geodetic survey. | CEPRO, Czech Republic (Slapanov) | Reconstruction of existing ramps for fuel loading and facilities including injection of additives. Turnover of fuels: 91 000 MTPY. |
Fuel loading facility | Ropa a plyn | 1997 | Česká republika | Design package, supervision, geodetic survey. | CEPRO, Czech Republic (Smyslov) | Reconstruction of fuel loading ramps and facilities including injection of additives. Turnover of fuels: 77 000 m3/year. |
Hydrocarbon vapors recovery | Ropa a plyn | 1997 | Česká republika | Design package, supervision. | CEPRO, Czech Republic (Smyslov) | Hydrocarbon recovery unit. Capacity: 120 m3/ hour |
Hydrocarbon vapors recovery | Ropa a plyn | 1997 | Česká republika | Design package, supervision. | CEPRO, Czech Republic (Vcelna) | Hydrocarbon recovery unit. Capacity: 120 m3/ hour. |
Reconstruction of Fuel loading station | Ropa a plyn | 1997 | Česká republika | Design package, supervision, geodetic works. | CEPRO, Czech Republic | Reconstruction of fuel loading ramps and facilities including injection of additives. Turnover of fuels: 81 000 m3/year. |
Pentane tank farm | Ropa a plyn | 1997 | Česká republika | Detail design | Kaucuk, Kralupy, Czech Republic | Engineering for direct pumping of pentane from Ceska Rafinerska storage vessels, into polymerization reactors. Capacity: 500 l/min., Transport height - 65m, Lenght - 1 300 m |
Phosphate fertiliser filtration | Ostatní chemie | 1996 | Česká republika | Design package, supervision. | Fosfa, Breclav- Postorna, Czech Republic | Filter press of dinatrium - hydrogen - phosphate suspension and filter press of neutralising calcium and phosphoric sludge. Capacity: 5 MTPH |
Cooling system revamping | Úprava vody a odpadních vod | 1996 | Česká republika | Optimisation study. | Ceska rafinerska, a.s. Kralupy, Czech Republic | Capacity: 10 000 m3/hour. |
Oily water separation system for Slapy dam | Úprava vody a odpadních vod | 1996 | Česká republika | Basic and Detail design, Supervision. | CEZ Prague, Czech Republic | XXXX |
Waster water treatment from prouction of biodiesel | Úprava vody a odpadních vod | 1996 | Česká republika | Basic and Detail design, Supervision. | MILO, Olomouc, Czech Republic | Biological waster water treatment plant. Capacity: 15 MTPD |
Desalination unit | Úprava vody a odpadních vod | 1996 | Česká republika | Basic and Detail design | Diamo, Straz pod Ralskem, Czech Republic | Decontamination of acidic underground waste water resulting from underground leaking of Uranium ores by means of reverse electrodialysis, evaporation and crystallisation. Capacity: 330 m3/hour of purified water. |
Bulk fuel storage facility Chemoprojekt, a.s. | Ropa a plyn | 1996 | Slovenská republika | Design package, environmental impact assessment, subcontractor tendering, start-up assistance,geologic and geodetic survey. | ŐMV Slovak Republic | Storage capacity: 4 000 m3, intake, storage and distribution of fuels on the west territory of Slovak Republic. |
Hydrocarbon vapors recovery | Ropa a plyn | 1996 | Česká republika | Design package, supervison. | Spolana, a.s., Czech Republic | Reconstruction of fuel tanking ramps, product addivation, Hydrocarbon vapours recovery - 120 m3/hour. Turnover of fuels: 170 000 m3/year. |
Isomeric linear alpha olefins (LAO production) | Ropa a plyn | 1996 | Česká republika | General reconstruction, planning and building permit documentation, basic technological specifications, design basis processing, environmental impact assessment, EPS, accident monitoring system, gas leak detection. | Spolana, a.s., Czech Republic | Fraction ratio: LAO C16/C18 = 1/1. Capacity: app. 5000 MTPY |
Biodiesel unit | Bionafta | 1996 | Česká republika | EP project (Detail Design) | Agropodnik a.s., Dobronín | Glycerine production 60% Capacity: 2 000 MTPY Technology: Agro |
Fire safety evaluation study for petrochemical complex | Ropa a plyn | 1996 | Česká republika | Fire hazard analysis in compliance with Czech fire codes. | Chemopetrol, Litvinov, a.s , Czech Republic | Petrochemistry objects - polyolefin section. |
Acetylene production and loading | Ostatní chemie | 1995 | Česká republika | Study + environmental impact assessment for implementation of technology. basic construction specifications, mechanical and technology layout, electro part. | Aga Gas, Praha, Czech Republic | Capacity: 1000 MTPY |
Reconstruction of sulphuric acid unit | Ostatní chemie | 1995 | Lebanon | Detail design | Lebanon Chemical, Lebanon | Capacity: 1500 MTPD. |
Fire hazard analyses | Ropa a plyn | 1995 | Česká republika | Fire hazard study in compliance with the Czech codes. (Code No.: 91/1995 Sb, documentation elaborated in the scope specified by the code No.: MV 21/1996 Sb.) | Koramo Kolin, Czech Republic | Mineral oil refinery |
Gama – butyrobetaine unit | Ostatní chemie | 1994 | Česká republika | Design documentation for building permit, detail design, supervision, environmental impact assessment. | Synthesia, a.s., Czech Republic | Batch production of gama-butyrobetaine including material and end product storage. End product is used in production of Carnitin. |
CCR unit | Ropa a plyn | 1993 | Česká republika | Detail design, Procurement | Ceska rafinerska, Czech Republic | Process licence: IFP Capacity: 450 000 MTPY |
Biodiesel unit | Bionafta | 1993 | Česká republika | Turn-key | MILO Olomouc, Czech Republic | Batch process: Vogel Noot Capacity: 30 000 MTPY |
Crude oil refinery | Ropa a plyn | 1990 | Irák | Basic and Detail design of hydrotreaters, reformer and off-sites of the refinery | TECHCORP, Iraq | Complete design of some units. Capacity: 6 mil. MTPY |
Lube oil complex | Ropa a plyn | 1984 | Irák | Complete design of the off-sites facilities. | SCOP, Iraq | Lube oil complex - tankfarm. |
Gas treatment plant and gas pipeline | Ropa a plyn | 1982 | Sýrie | XXXX | Syrian Petroleum Company | Natural gas treatment plant DEA sweeting Salzgitter Lummus process. Construction of 600 km of gas pipeline from Homs to Jbisseh. |
Crude oil refinery-Sallahuddin refinery II | Ropa a plyn | 1981 | Irák | Detail design | SEORGI, Iraq | Crude oil refinery, fuel type. Capacity: 3,5 mil. MTPY |
Aniline unit | Anilin | 1989 | Česká republika | Basic design | MCHZ Ostrava, Czech Republic | Construction of a new unit Capacity: 65 000 MTPY |
Crude oil refinery | Ropa a plyn | 1978 | Irák | Detail design | SEORGI, Iraq | Crude oil refinery, fuel type. Capacity: 3,5 mil. MTPY |
Oil refinery expansion | Ropa a plyn | 1976 | Irák | Basic and Detail design | SCOP, Iraq | Expansion of crude oil refinery. Capacity: 3,5 mil. MTPY |
Crude oil refinery | Ropa a plyn | 1970 | Irák | Detail design, Supervision, SU | OPCA, Iraq | Complete crude oil refinery. Capacity: 3,5 mil. MTPY |
Crude oil refinery | Ropa a plyn | 1957 | Sýrie | Detail design | Homs, Syria | Complete crude oil refinery, fuel type, 5 of 6 stages. Capacity: 3,9 mil. MTPY |